[ Prev ]    Page:   1    2    3    4    5    6    7    8    [ Next ]

PDF version for print


Installation Floor Plan

 

Installation of ECO series is easy, quick and cost effective on materials and labour. Following are basic procedure for floor plan recommended in most of the cases. As a matter of fact, the system itself enables Netfloor installers often invent smarter solution during installation.

 
  1. Select two longest right-angle walls as starting lines for first rows full size UniPanel.
  2. First step, apply Sound Attenuation Blanket.
  3. Then, plan the first piece UniPanel at the right-angle or recess to measure the 2 starting lines as shown at the drawing below. Connecting first row UniPanel by half-size Base Connector along the starting walls. Allow 2 mm allowance between UniPanel and wall in order to avoid squeeze due to deviation of the wall.
  4. Continuous connection of UniPanel by Base Connector is simple and quick. Steel Trench Cap may be installed before or after routing of cables.
  5. Ramps and perimeters installation plan shown at drawing below.
 

 